You can't git clone a gigawatt

There's always a moat in tech. It just moves. From Windows apps to user feedback, the hard thing to copy changes. My next bet is electricity.

Jack Dorsey says there is no moat, and Elon Musk says Sparta never had one. Meanwhile, Musk’s own company reported running 69 gas turbines in July 2026 to keep Grok’s data centers powered. How long would it take to copy that software moat?

There’s always a moat in tech. It just moves.

Timeline of copying a moat. A git clone takes seconds and open models lag by months. A transformer and a power project on the largest US grid take years.
Embed this GIF
<a href="https://argbe.tech/blog/software-moats-electricity"><img src="https://argbe.tech/media/software-moats-electricity.gif" alt="Timeline of copying a moat. A git clone takes seconds and open models lag by months. A transformer and a power project on the largest US grid take years." width="800" height="1000"></a>

How the moat moved

A working agent loop can be copied. The history of how your users interact with your AI agents doesn’t come with it.

How long it takes to copy a software moat

Downloading code, matching a benchmark and connecting a power plant measure different things. The comparison shows different timescales, not how long it takes to win customers.

What takes timeReported durationWhat the number measures
Open models reaching earlier closed-model capabilityAbout 4 monthsEpoch AI’s May 2026 analysis: average lag since January 2026 on its capability index.
Procuring a power transformer128 weeks on average; up to 4 yearsWood Mackenzie’s Q2 2025 average and the IEA’s 2025 survey.
A generation project’s grid agreement in PJM40 months on averageCarbon Direct’s May 2026 analysis. This concerns power generation, not a data center’s connection request.
Projects reaching operation in PJMMore than 7 years on averageData Center Knowledge’s May 2026 report of PJM data, for projects entering service in 2025. Includes work after approval; not a general data-center hookup time.

Next, my bet: electricity

A November 2025 report quoted Satya Nadella describing “chips sitting in inventory that I can’t plug in.” His problem was getting powered data centers built fast enough.

PJM’s board estimated that data centers would account for roughly 30,000 of 32,000 MW of additional peak demand between 2024 and 2030. That’s about 94% of the projected growth in one region, not national electricity use.

The turbines show that a grid connection isn’t the only route. By late August, 11 had powered down under a plan to replace the temporary turbines with a permanent power plant. That still means building physical infrastructure.

A long wait alone doesn’t prove a lasting moat. And if power becomes one, a team renting compute meets it as a cost to control, not an advantage it owns.

Agents make code cheaper to copy. They don’t make a transformer arrive sooner.

You can git clone code. You can’t git clone a gigawatt.